1. New building
New Construction of Valvoline Instant Oil Change with Lube Pit
From Monday, Aug 31 through Sunday, Sep 6, 2026, 41 commercial projects entered or moved through City of Austin plan review and 55 commercial building permits were issued. 1 plan review case and 8 issued permits rate Strong or Medium for Glazing / Storefront work.
This archived issue is ranked for Glazing / Storefront work only, best fits first. Weekly Digest shows the whole week; Daily Recap shows Friday, Sep 4.
41 commercial projects in city plan review and 55 newly issued commercial building permits that week. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. 40 of the issued permits were previously in plan review and are marked, so nothing shows up twice.
New Construction of Valvoline Instant Oil Change with Lube Pit
Temporary Office/Jobsite Trailer - no public access - no plumbing ATTN ELEC INSP: REVISED PANEL SCHEDULE AND LOAD CALC FOR PANEL SUPPLYING TRAILER REQUIRED
Exterior garage facade glazing, louvers, and structural attachments (installing Ranger RUG 700 2 1/2" x 7" glazing system and Ruskin Louver EME720)
REPLACING 4 WINDOWS, like for like, IN EXISTING RESIDENTIAL SPACE
Interior Remodel to Existing Garage Space. Scope of work includes removal of exterior windows for new garage doors with metal ramps annd stairs. New F
New construction of multifamily - 3 story residences over 2 story parking - total 5 stories Bldgs A B and C New construction of multifamily - 3 story residences over 2 story parking - total 5 stories Bldgs A B and C New construction of multifamily - 3 story…
Addition and Change of Use from Transportation Terminal to Restaurant (2131 SF).
Austin Art in Public Places (ACME) new public artwork. (Fees Waived)
New Construction Office Warehouse Building 3 New Construction Office Warehouse Building 4
New Ground up Shell Building and Interior Grocery Store.
+36 more plan review cases in the full issue
+50 more issued permits in the full issue
How fit is scored for glazing and storefront work: points for size (square feet), scope (new buildings, shells, additions and finish-outs by trade) and explicit glazing wording (storefront, curtain wall, glazing, windows, facade). Strong needs explicit trade scope or a qualifying job of 10,000+ SF; small pieces of larger projects are flagged and capped at Medium.
Showing the top leads in each section for the week of Aug 31–Sep 6, 2026.
Start Your Free Trial7 commercial projects in city plan review and 13 newly issued commercial building permits that day. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. Every Daily Recap also includes the full spreadsheet with every Plan Review case and issued permit. 11 of the issued permits were previously in plan review and are marked, so nothing shows up twice.
REPLACING 4 WINDOWS, like for like, IN EXISTING RESIDENTIAL SPACE
Reroof - emergency department and postpartum. Existing hospital
Remodel at existing community college facility. Replace exterior exit stairs
Change of use: Office/Business to Adult Care Services; no construction
Change of use and an interior remodel to create an office
New construction of multifamily - 3 story residences over 2 story parking - total 5 stories Bldgs A B and C
New construction of an Level 8 swimming pool at approved site.
Interior Non-Structural Finish Out
Remove existing PVC and fanfold cover board down to original BUR mechanically attach fan fold and 50mil single-ply PVC membrane 1 Admin
Remove existing PVC and fanfold cover board down to original BUR mechanically attach fan fold and 50mil single-ply PVC membrane 3 Fuel
+2 more plan review cases in the full issue
+8 more issued permits in the full issue
How fit is scored for glazing and storefront work: points for size (square feet), scope (new buildings, shells, additions and finish-outs by trade) and explicit glazing wording (storefront, curtain wall, glazing, windows, facade). Strong needs explicit trade scope or a qualifying job of 10,000+ SF; small pieces of larger projects are flagged and capped at Medium.
Showing the top leads in each section for Friday, Sep 4, 2026.
Start Your Free Trial| Plan Review or Issued Permit | Address / Project | Work | Valuation | Company | Fit (Glazing / Storefront) |
|---|---|---|---|---|---|
| Plan Review | Commercial remodel | Remodel | N/A | N/A | Low |
| Plan Review | Hospital remodel | Remodel | N/A | St Davids Healthcare | Low |
| Plan Review | Commercial remodel | Remodel | $327K est. (TDLR filing) | N/A | Low |
| Plan Review | Change of use to adult care services | Remodel | N/A | N/A | Low |
| Plan Review | Change of use to office building | Remodel | N/A | Trinity WAY LLC | Low |
| Issued Permit | 9-story apartment building | New | $10.1M | DMJ Construction Services LLC | Medium |
A preview of 6 rows and 6 of the 36 columns. Every Daily Recap issue includes the full spreadsheet with every lead, company contacts (never individuals' names), phones, status, dates, fit for each trade and record links.
Data: City of Austin, Development Services Department open data (Plan Review Cases and Issued Construction Permits). Austin Permit Leads is not affiliated with or endorsed by the City of Austin. Always confirm details in the official record.