1. 2-story manufacturing plant
New construction of a two-story manufacturing facility consisting of a main factory (1,220,632 SF) with an attached two-story office (
From Monday, Aug 3 through Sunday, Aug 9, 2026, 51 commercial projects entered or moved through City of Austin plan review and 50 commercial building permits were issued. 3 plan review cases and 7 issued permits rate Strong or Medium for Roofing work.
This archived issue is ranked for Roofing work only, best fits first. Weekly Digest shows the whole week; Daily Recap shows Friday, Aug 7.
51 commercial projects in city plan review and 50 newly issued commercial building permits that week. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. 40 of the issued permits were previously in plan review and are marked, so nothing shows up twice.
New construction of a two-story manufacturing facility consisting of a main factory (1,220,632 SF) with an attached two-story office (
ePlan Review: New Shell Building, New Parking Garage, Demised Tenant Space 100, Demised Tenant Space 110, Demised Tenant Space 120, Demised Tenant Space 130 6…
Interior Remodel to Existing Building to Accommodate New Manufacturing Equipment, Scope of Work include Re- Circuiting of Existing Panels, and the Addition of Pre
Roof replacement for existing AISD ES (2 apps - Buildings C and D)
QT - Install new 848.46kW rooftop solar system to existing commercial only
New Construction of Medical Office Building with New Parking Garage (75766 SF). New Construction of Parking Garage (75766 SF).
Simple Re-Roof. Existing retail.
Re-roof & Overlay
Remove and replace existing galvalume roof on 100 X 100 building with new vinyl reinforced fiberglass insulation. Existing warehouse.
Construction of a new building addition and alteration to an existing two-story private club. Conventionally framed wood structure on a slab-on-ground steel-reinforced concrete slab.
+46 more plan review cases in the full issue
+45 more issued permits in the full issue
How fit is scored for roofing work: points for size (square feet), scope (new buildings, shells, additions and finish-outs by trade) and explicit roofing wording (re-roof, roof, TPO, membrane). Strong needs explicit trade scope or a qualifying job of 10,000+ SF; small pieces of larger projects are flagged and capped at Medium.
Showing the top leads in each section for the week of Aug 3–9, 2026.
Start Your Free Trial7 commercial projects in city plan review and 6 newly issued commercial building permits that day. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. Every Daily Recap also includes the full spreadsheet with every Plan Review case and issued permit. 4 of the issued permits were previously in plan review and are marked, so nothing shows up twice.
Change of use religous services to pet services
Remove demising wall to expand suite into adjacent areas. Phase 1 scope. (2 Apps, Suite 200 and 201)
SMALL PROJECT - T-Mobile plans to install: 1 platform, 6 antennas, 6 radios and associated cabling, (1) 10'x13' canopy, 1 GPS antenna, 1 PPC, 4 LED flood lights, 1…
Change of Use from Fitness to Coffee Shop - Interior finish-out and renovation of an existing tenant space for a coffee shop. Scope includes construction of customer…
Finish out of an existing shell space for medical office
Remove and replace existing galvalume roof on 100 X 100 building with new vinyl reinforced fiberglass insulation. Existing warehouse.
Change of use to Medical Office and Remodel.
CHANGE OF USE MED OFFICE TO RETAIL with interior renovation of approx 3050 SF retail space including new partitions finishes fixtures and associated MEP modifications.
Interior remodel to admin/buisiness office.
Removal of Non-Bearing Interior Partition Walls Only. No Structural Mechanical Electrical Plumbing Fire Protection or Occupancy Changes. Conversion of Office into Out patience Rehabilitation Therapy Area 2026-073219 DA - Approved
+2 more plan review cases in the full issue
+1 more issued permit in the full issue
How fit is scored for roofing work: points for size (square feet), scope (new buildings, shells, additions and finish-outs by trade) and explicit roofing wording (re-roof, roof, TPO, membrane). Strong needs explicit trade scope or a qualifying job of 10,000+ SF; small pieces of larger projects are flagged and capped at Medium.
Showing the top leads in each section for Friday, Aug 7, 2026.
Start Your Free Trial| Plan Review or Issued Permit | Address / Project | Work | Valuation | Company | Fit (Roofing) |
|---|---|---|---|---|---|
| Plan Review | Change of use to pet services | Remodel | N/A | Cleantag LLC | Low |
| Plan Review | Commercial remodel | Remodel | $500K est. (TDLR filing) | N/A | Low |
| Plan Review | Telecom site remodel | Remodel | N/A | COA Wuest Group | Low |
| Plan Review | Change of use to retail space | Remodel | $280K est. (TDLR filing) | N/A | Low |
| Plan Review | Medical clinic remodel | Remodel | N/A | St Davids Healthcare Partnership LP LLP | Low |
| Issued Permit | Warehouse remodel | Remodel | $516K est. (TDLR filing) | Diamond J Buildings LLC | Medium |
A preview of 6 rows and 6 of the 36 columns. Every Daily Recap issue includes the full spreadsheet with every lead, company contacts (never individuals' names), phones, status, dates, fit for each trade and record links.
Data: City of Austin, Development Services Department open data (Plan Review Cases and Issued Construction Permits). Austin Permit Leads is not affiliated with or endorsed by the City of Austin. Always confirm details in the official record.