1. 10-story apartment building
Remodel of existing building and New construction addition to create a Mixed Use MF building. 102,878 SF of R occupancy among 27 dwelling units; with accessory uses of…
Permit expediter: Mercury Permits Inc
From Monday, Jul 6 through Sunday, Jul 12, 2026, 51 commercial projects entered or moved through City of Austin plan review and 50 commercial building permits were issued. 3 plan review cases and 12 issued permits rate Strong or Medium for Glazing / Storefront work.
This archived issue is ranked for Glazing / Storefront work only, best fits first. Weekly Digest shows the whole week; Daily Recap shows Friday, Jul 10.
51 commercial projects in city plan review and 50 newly issued commercial building permits that week. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. 35 of the issued permits were previously in plan review and are marked, so nothing shows up twice.
Remodel of existing building and New construction addition to create a Mixed Use MF building. 102,878 SF of R occupancy among 27 dwelling units; with accessory uses of…
Interior Remodel and Change of Use from Historic Home to Restaurant. Scope of Work to include Remodel of an Existing Historic house (3,054 SF) and adding on a Glas
Single-Story New Construction Addition - Phase 2: Mercantile Occupancy Shell Space (Phase 1 Permit Case #)
Repairing storefront, like for like
5 window replacements. Existing multifamily unit
Remodel of restrooms on the first and second levels; new window openings in the existing exterior walls at weight room; new roof top skylights lighting and acoustical tiles at corridor north of competition gym
Exterior Remodel Only: Repair and Replace Staircase & Railing. Replace all rotten wood to new like to like support posts facia boards stair strings door & window trims & paint around building (8) Applications Exterior Remodel Only: Repair and Replace…
New Construction of an Express Car Wash.
ePlan: Expedited Review - New Construction of 7 4-Story Multi-Family Bldg. (425647 SF).
New Construction of a Religious Worship Facility.
+46 more plan review cases in the full issue
+45 more issued permits in the full issue
How fit is scored for glazing and storefront work: points for size (square feet), scope (new buildings, shells, additions and finish-outs by trade) and explicit glazing wording (storefront, curtain wall, glazing, windows, facade). Strong needs explicit trade scope or a qualifying job of 10,000+ SF; small pieces of larger projects are flagged and capped at Medium.
Showing the top leads in each section for the week of Jul 6–12, 2026.
Start Your Free Trial10 commercial projects in city plan review and 10 newly issued commercial building permits that day. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. Every Daily Recap also includes the full spreadsheet with every Plan Review case and issued permit. 7 of the issued permits were previously in plan review and are marked, so nothing shows up twice.
Interior Remodel and Change of Use from Historic Home to Restaurant. Scope of Work to include Remodel of an Existing Historic house (3,054 SF) and adding on a Glas
Single-Story New Construction Addition - Phase 2: Mercantile Occupancy Shell Space (Phase 1 Permit Case #)
5 window replacements. Existing multifamily unit
CHANGE OF USE OOFICE WAREHOUSE TO RETAIL WAREHOUSE No changes to building planned. Warehouse will accept donations of furniture and allow clients of nonprofit partners…
RE ROOF overlay existing modified with coating using new .6mil tpo. mechanically fastened at existing restaurant - OVA
New Construction of a Religious Worship Facility.
New Construction for POS (Pay Station Canopy) New Construction for 15 Bay Vacuum Canopy. New Construction for 6 Bay Vacuum Canopy New construction for dumpster enclosure
re-roof at existing senior living facility main building
TENANT FINISH OUT - LAW OFFICES
Partial remodel of existing convent housing building
+5 more plan review cases in the full issue
+5 more issued permits in the full issue
How fit is scored for glazing and storefront work: points for size (square feet), scope (new buildings, shells, additions and finish-outs by trade) and explicit glazing wording (storefront, curtain wall, glazing, windows, facade). Strong needs explicit trade scope or a qualifying job of 10,000+ SF; small pieces of larger projects are flagged and capped at Medium.
Showing the top leads in each section for Friday, Jul 10, 2026.
Start Your Free Trial| Plan Review or Issued Permit | Address / Project | Work | Valuation | Company | Fit (Glazing / Storefront) |
|---|---|---|---|---|---|
| Plan Review | Change of use to restaurant | Addition and Remodel | $1.0M | SoCo Legacy LLC dba Todd House LLC | Medium |
| Plan Review | Retail building | New | $200K est. (TDLR filing) | N/A | Medium |
| Plan Review | Apartment building remodel | Remodel | N/A | N/A | Low |
| Plan Review | Change of use to warehouse | Remodel | N/A | City of Austin, Austin Resource Recovery | Low |
| Plan Review | Restaurant remodel | Remodel | N/A | River City Roof Systems | Low |
| Issued Permit | Church | New | N/A | Civilitude LLC | Medium |
A preview of 6 rows and 6 of the 36 columns. Every Daily Recap issue includes the full spreadsheet with every lead, company contacts (never individuals' names), phones, status, dates, fit for each trade and record links.
Data: City of Austin, Development Services Department open data (Plan Review Cases and Issued Construction Permits). Austin Permit Leads is not affiliated with or endorsed by the City of Austin. Always confirm details in the official record.