1. Commercial remodel
Interior Remodel to Existing Condominium - All Existing Electrical and Mechanical to remain - Suite 1106
From Monday, Jan 19 through Sunday, Jan 25, 2026, 32 commercial projects entered or moved through City of Austin plan review and 26 commercial building permits were issued. 5 plan review cases and 4 issued permits rate Strong or Medium for Electrical work.
This archived issue is ranked for Electrical work only, best fits first. Weekly Digest shows the whole week; Daily Recap shows Friday, Jan 23.
32 commercial projects in city plan review and 26 newly issued commercial building permits that week. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. 16 of the issued permits were previously in plan review and are marked, so nothing shows up twice.
Interior Remodel to Existing Condominium - All Existing Electrical and Mechanical to remain - Suite 1106
CHANGE OF USE RETAIL TO FITNESS CENTER. Interior renovations, including mechanical, electrical, and plumbing
QT - Interior remodel, plumbing and electrical pmts rqd. - OVA
Installation of 29.10 KW Rooftop PV System for Existing Office/Warehouse
New construction of 3 story apartment building with 9 units and a parking garage
Interior Remodel to Existing Admin Office Areas on Floor 1. Phase1-C. Interior Remodel to Existing Admin Office Areas. Phase9-A. Phase9-B. Phase17-C. Phase9-C. Phase10-A. Phase10-B. Phase10-C. Phase11-A. Phase11-B. Phase11-C. Phase12-A. Phase12-B. Phase13-A.…
First Time Finish out from Warehouse Shell to Office Warehouse (41770 SF)
Installing 90.2 kW Solar System with 164 ALEX-550-W panels 1 SCA50KTL-DO and 1 SCA25KTL-DO Inverters.
relocation of 2 doors connecting 400 amp meter and 800 amp meter/service.
Interior remodel of existing office space dividing full floor into new spec suite 200
+27 more plan review cases in the full issue
+21 more issued permits in the full issue
How fit is scored for electrical work: points for size (square feet), scope (new and shell buildings score highest, small remodels lowest), occupancy (labs, data, medical, hotels, grocery and industrial carry the most electrical load) and explicit electrical wording (service upgrade, switchgear, transformer, generator, EV charging, lighting, solar). Strong needs real size (20,000+ SF) or explicit electrical scope; small pieces of larger projects are flagged and capped at Medium.
Showing the top leads in each section for the week of Jan 19–25, 2026.
Start Your Free Trial10 commercial projects in city plan review and 9 newly issued commercial building permits that day. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. Every Daily Recap also includes the full spreadsheet with every Plan Review case and issued permit. 7 of the issued permits were previously in plan review and are marked, so nothing shows up twice.
Installation of 29.10 KW Rooftop PV System for Existing Office/Warehouse
After the fire, we plan to replace damaged electrical components and change the electrical panel, remove and reinstall portions of the exterior wall to support the…
Tenant remodel Expansion for Cat Hospital HVAC - Replacement and slight location change of register grilles only. This is exempt from Mechanical permit
Interior alteration to remove social/communicating stair in an existing office space on levels 9-12 (7 Day Application)
Interior remodel to existing business office suite. No access control
Interior Remodel to Existing Admin Office Areas on Floor 1. Phase1-C. Interior Remodel to Existing Admin Office Areas. Phase9-A. Phase9-B. Phase17-C. Phase9-C. Phase10-A. Phase10-B. Phase10-C. Phase11-A. Phase11-B. Phase11-C. Phase12-A. Phase12-B. Phase13-A.…
Installing 90.2 kW Solar System with 164 ALEX-550-W panels 1 SCA50KTL-DO and 1 SCA25KTL-DO Inverters.
INTERIOR REMODEL OF EXISTING OFFICE SPACE.
Remodel of existing restaurant finish out
7 day interior remodel of existingadmin space
+5 more plan review cases in the full issue
+4 more issued permits in the full issue
How fit is scored for electrical work: points for size (square feet), scope (new and shell buildings score highest, small remodels lowest), occupancy (labs, data, medical, hotels, grocery and industrial carry the most electrical load) and explicit electrical wording (service upgrade, switchgear, transformer, generator, EV charging, lighting, solar). Strong needs real size (20,000+ SF) or explicit electrical scope; small pieces of larger projects are flagged and capped at Medium.
Showing the top leads in each section for Friday, Jan 23, 2026.
Start Your Free Trial| Plan Review or Issued Permit | Address / Project | Work | Valuation | Company | Fit (Electrical) |
|---|---|---|---|---|---|
| Plan Review | Warehouse remodel | Remodel | N/A | Freedom Solar Power | Medium |
| Plan Review | Commercial remodel | Remodel | N/A | Everest Liquor | Low |
| Plan Review | Hospital remodel | Remodel | N/A | MedTech Construction | Low |
| Plan Review | Office space remodel | Remodel | $3M est. (TDLR filing) | Cshv-300 West 6TH Street LLC | Low |
| Plan Review | Office space remodel | Remodel | N/A | N/A | Low |
| Issued Permit | Office space remodel | Remodel | $50K est. (TDLR filing) | Structure Tone | Medium |
A preview of 6 rows and 6 of the 36 columns. Every Daily Recap issue includes the full spreadsheet with every lead, company contacts (never individuals' names), phones, status, dates, fit for each trade and record links.
Data: City of Austin, Development Services Department open data (Plan Review Cases and Issued Construction Permits). Austin Permit Leads is not affiliated with or endorsed by the City of Austin. Always confirm details in the official record.