Archive · Week of Aug 10–16, 2026 · Electrical

Austin Electrical Permit Leads: Aug 10–16, 2026

From Monday, Aug 10 through Sunday, Aug 16, 2026, 56 commercial projects entered or moved through City of Austin plan review and 49 commercial building permits were issued. 9 plan review cases and 17 issued permits rate Strong or Medium for Electrical work.

This archived issue is ranked for Electrical work only, best fits first. Weekly Digest shows the whole week; Daily Recap shows Friday, Aug 14.

Austin Permit Leads · Weekly Digest

Week of Aug 10–16, 2026

56 commercial projects in city plan review and 49 newly issued commercial building permits that week. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. 38 of the issued permits were previously in plan review and are marked, so nothing shows up twice.

In Plan Review: Week of Aug 10–16

Issued Permits: Week of Aug 10–16

1. Substation electrical building, Walnut Creek WWTP

New this week (applied Aug 14)
New · applied Aug 14 · Approved as of Oct 29, 2026 · 10,789 SF
Electrical: Strong fit · score 77

New Substation 4 C71 Electrical Building at Walnut Creek WWTP

Architect/Engineer: Atlas Design Services
View on City of Austin AB+C Portal

2. Multifamily shell building

New this week (applied Aug 13)
New · applied Aug 13 · Awaiting Update - Fee Paid · 277,177 SF · $45.0M
Electrical: Strong fit · score 70

New Construction of Shell- Scope of Work to Include Multi Family Res. Shell and Tenant Finish out 1st Floor Multifamily and Amenity sp

Civil engineer (site plan): Kimley-Horn and Associates (from 2025 site plan SP-2025-0340C.SH)
Permit expediter: KS Permitting LLC
View on City of Austin AB+C Portal

3. Warehouse with repair garage

Moved to Awaiting Update Aug 11
New · applied Jul 24 · Awaiting Update · 11,850 SF · $200K est. (TDLR filing)
Electrical: Strong fit · score 70

New Construction: 11,850 Sq. Ft. Open-Face Warehouse SP-2025-0172C - Concurrent Review ATTN ELEC INSP: All grounding electrodes as described in 250.52(A)(1) through…

Architect/Engineer: LRG Engineering LLC
View on City of Austin AB+C Portal

4. Change of use to office building

New this week (applied Aug 10)
Remodel · applied Aug 10 · Approved as of Sep 24, 2026
Electrical: Medium fit · score 48

Change of use to admin/business office and small tenant improvement project, renovate break room and bathroom, change out lighting throughout

GC or design-builder: Stain Construction LLC
View on City of Austin AB+C Portal

5. Change of use to retail space

New this week (applied Aug 13)
Remodel · applied Aug 13 · Approved as of Sep 4, 2026
Electrical: Medium fit · score 48

CHANGE OF USE to Retail Sports: Interior remodel of an existing space, including new lighting for a retail sports and collector cards occupancy. - Approved

Applicant: Pritchett Consulting Group
View on City of Austin AB+C Portal

1. Hotel remodel

Permit issued Aug 10
Remodel · 13,561 SF · issued Aug 10
Electrical: Strong fit · score 79

Finish Out for Hotel Rooms Housekeeping Hydration station and Electrical/IDF Room Floor 9 Finish Out for Hotel Rooms Housekeeping Hydration station and Electrical/IDF Room Floor 10 Finish Out for Hotel Rooms Housekeeping Hydration station and Electrical/IDF…

GC or design-builder: DPR Construction
View on City of Austin AB+C Portal

2. 2-story manufacturing plant

Permit issued Aug 13
New · 62,758 SF · $12.3M · issued Aug 13
Electrical: Strong fit · score 70

62435 SF ground up new light manufacturer. Project will be structural steel tilt wall construction with associated site work and interior finish out. New Dumpster Enclosure for New Light Manufacturing Facility. (323 sq ft)

GC or design-builder: Kingham Dalton Wilson
View on City of Austin AB+C Portal

3. Manufacturing plant remodel

Permit issued Aug 13
Remodel · 216,060 SF · $4M est. (TDLR filing) · issued Aug 13
Electrical: Strong fit · score 67

Finish out for Light Manufacturing for Bldg. 3

GC or design-builder: Zapalac
View on City of Austin AB+C Portal

4. Retail space remodel

Permit issued Aug 10
Remodel · 7,475 SF · $200K est. (TDLR filing) · issued Aug 10
Electrical: Medium fit · score 60

Scope includes providing new wall finishes new lighting fixtures new kitchen area and interior walls storefronts for office use. Scope will include mechanical electrical and plumbing upgrades.

GC or design-builder: Owrey Construction
View on City of Austin AB+C Portal

5. Retail space remodel

Permit issued Aug 10
Remodel · 2,997 SF · $1.5M est. (TDLR filing) · issued Aug 10
Electrical: Medium fit · score 54

Remodel for existing tenant. Relocation of interior door and window. Addition of interior storefront and non-structural columns for power and data conduits.

GC or design-builder: Property Resolve, LLC
View on City of Austin AB+C Portal

+51 more plan review cases in the full issue

+44 more issued permits in the full issue

How fit is scored for electrical work: points for size (square feet), scope (new and shell buildings score highest, small remodels lowest), occupancy (labs, data, medical, hotels, grocery and industrial carry the most electrical load) and explicit electrical wording (service upgrade, switchgear, transformer, generator, EV charging, lighting, solar). Strong needs real size (20,000+ SF) or explicit electrical scope; small pieces of larger projects are flagged and capped at Medium.

Showing the top leads in each section for the week of Aug 10–16, 2026.

Start Your Free Trial
Austin Permit Leads · Daily Recap

Friday, Aug 14, 2026

13 commercial projects in city plan review and 5 newly issued commercial building permits that day. Best fits first: in each issue, every section opens with up to 10 Strong or Medium fits as full cards, then compact rows for other leads with a company contact or a Medium+ fit; low-fit leads with no company contact are counted at the end of each section. Shown here: the top 5 in each section by ranking, whatever their fit. Every Daily Recap also includes the full spreadsheet with every Plan Review case and issued permit. 3 of the issued permits were previously in plan review and are marked, so nothing shows up twice.

In Plan Review: Fri, Aug 14

Issued Permits: Fri, Aug 14

1. Substation electrical building, Walnut Creek WWTP

New today (applied Aug 14)
New · applied Aug 14 · Approved as of Oct 29, 2026 · 10,789 SF
Electrical: Strong fit · score 77

New Substation 4 C71 Electrical Building at Walnut Creek WWTP

Architect/Engineer: Atlas Design Services
View on City of Austin AB+C Portal

2. Office space remodel

New today (applied Aug 14)
Remodel · applied Aug 14 · Approved as of Oct 20, 2026 · $264K est. (TDLR filing)
Electrical: Medium fit · score 48

Interior tenant improvement to existing commercial office space. Install one new sink connected to existing plumbing and add electrical receptacles. No structural…

Owner/Developer: 1023 Holdings, LLC (from 2022 site plan SP-2022-0019C)
View on City of Austin AB+C Portal

3. Apartment building remodel with garage

Moved to Awaiting Update Aug 14
Remodel · applied Jul 31 · Awaiting Update · $350K est. (TDLR filing)
Electrical: Medium fit · score 43

SMALL PROJECT - Installation of 6 EV Chargers (3 Dual-Ports) in parking garage at existing multifamily residential property

Trade contractor: Smart Charge Residential LLC
View on City of Austin AB+C Portal

4. Commercial remodel

New today (applied Aug 14)
Remodel · applied Aug 14 · Approved as of Aug 21, 2026 · $75K est. (TDLR filing)
Electrical: Medium fit · score 43

Install cmu wall at exterior for future meter bank

Owner/Developer: Connor Lane Austin Owner, LP (from 2022 site plan SP-2022-0502C)
Permit expediter: Bennett Consulting
View on City of Austin AB+C Portal

5. Commercial remodel

New today (applied Aug 14)
Remodel · applied Aug 14 · Approved as of Sep 15, 2026
Electrical: Low fit · score 35

Partial demolition of walls, ceilings, hvac & lighting equip. build new walls, install new hvac, lighting new fixtures, cabinets, etc. re-use existing bathrooms

Architect/Engineer: Knight Group Architecta
View on City of Austin AB+C Portal

1. Commercial remodel

Permit issued Aug 14
Remodel · 5,000 SF · issued Aug 14
Electrical: Medium fit · score 46

Minot remodel of existing tenant space to demo existing interior improvements relocate doors add 6 new electrical J box whips to new furniture and update access control from previous expired permit. No plumbing or mech scope

GC or design-builder: HRNCIR Construction, LP
View on City of Austin AB+C Portal

2. Addition, clubhouse

Permit issued Aug 14
Addition · 35,768 SF · $120K est. (TDLR filing) · issued Aug 14
Electrical: Medium fit · score 40

Smart Housing Project - remodel and addition to existing historic bldg to convert to 30 resd units comprised of 14415 sqft of remodel space + 1805 sf porch area (remodel space) + and 6870 sqft of new construction + 23090 sqft. (Building 1) Smart Housing…

GC or design-builder: Skybeck Construction, LLC
View on City of Austin AB+C Portal

3. 2-story parking garage

Permit issued Aug 14
New · $1.5M · issued Aug 14
Electrical: Low fit · score 28

New Parking Garage/Sprink

No company contact in the City data.
View on City of Austin AB+C Portal · Open the case link and check People Details for contact information.

4. Warehouse remodel

Permit issued Aug 14
Remodel · building size 71,659 SF · $800K est. (TDLR filing) · issued Aug 14
Electrical: Low fit · score 18

Interior Remodel to Existing Warehouse Office

GC or design-builder: Gordon Highlander
View on City of Austin AB+C Portal

5. School remodel

Permit issued Aug 14
Remodel · 1,500 SF · $20M est. (TDLR filing) · issued Aug 14
Electrical: Low fit · score 13

Relocation of 5 existing portables on the existing school campus site.

GC or design-builder: R.L. Hicks L.P.
View on City of Austin AB+C Portal

+8 more plan review cases in the full issue

How fit is scored for electrical work: points for size (square feet), scope (new and shell buildings score highest, small remodels lowest), occupancy (labs, data, medical, hotels, grocery and industrial carry the most electrical load) and explicit electrical wording (service upgrade, switchgear, transformer, generator, EV charging, lighting, solar). Strong needs real size (20,000+ SF) or explicit electrical scope; small pieces of larger projects are flagged and capped at Medium.

Showing the top leads in each section for Friday, Aug 14, 2026.

Start Your Free Trial

Daily Recap Spreadsheet Preview

Daily Recap Feature
Plan Review or Issued PermitAddress / ProjectWorkValuationCompanyFit (Electrical)
Plan ReviewSubstation electrical building, Walnut Creek WWTPNewN/AAtlas Design ServicesStrong
Plan ReviewOffice space remodelRemodel$264K est. (TDLR filing)1023 Holdings, LLCMedium
Plan ReviewApartment building remodel with garageRemodel$350K est. (TDLR filing)Smart Charge Residential LLCMedium
Plan ReviewCommercial remodelRemodel$75K est. (TDLR filing)Connor Lane Austin Owner, LPMedium
Plan ReviewCommercial remodelRemodelN/AKnight Group ArchitectaLow
Issued PermitCommercial remodelRemodelN/AHRNCIR Construction, LPMedium

A preview of 6 rows and 6 of the 36 columns. Every Daily Recap issue includes the full spreadsheet with every lead, company contacts (never individuals' names), phones, status, dates, fit for each trade and record links.

← Previous WeekAll WeeksNext Week →

Data: City of Austin, Development Services Department open data (Plan Review Cases and Issued Construction Permits). Austin Permit Leads is not affiliated with or endorsed by the City of Austin. Always confirm details in the official record.